alt alt
GSM BTS Site Build – MTN Nigeria

Location:

Nigeria

Owner:

MTN Nigeria

Duration / Finish:

12 months / 2006

Description :

Turnkey Contract for the Construction of GSM BTS Sites

Scope of Work :

 

Project and Construction Management, logistics and site Installation supervision for the construction  of GSM BTS sites in, Nigeria.

Scope included site acquisition, site clearing, civil works, supply and erection of steel lattice towers, palisade fencing, fully reticulated air-conditioned equipment shelters, AC power supplies, 17,5 kVA back-up generators with 2,000 litre fuel tanks, DC power supply, fire suppression systems, alarms, RF cables and antennas.

Compilation of all site and construction documentation.

The contract was awarded on a Turnkey basis

 

 
Likusasa Engineering & Contracting (Pty) Ltd
DH Digital - Web Development & Marketing