GSM BTS Site Build - Huawei Nigeria

Location:

Nigeria

Owner:

V-Mobile Nigeria / HUAWEI

Duration / Finish:

6 months / 2005

Description :

Supervision and Construction of  50 GSM BTS Sites

Scope of Work :

 

Project and Construction Management, procurement, material Management, logistics and site Installation supervision.

Pre-commissioning and Commissioning of 50 BTS sites in Nigeria. Scope included site acquisition, site clearing, civil works, supply and erection of steel lattice towers, palisade fencing, fully reticulated air-conditioned equipment shelters, AC power supplies, 27kVA back-up generators with 2,000 litre fuel tanks, DC power supply, fire suppression systems, alarms, RF cables and antennas.

Compilation of all site and construction documentation.

The contract was awarded on a Turnkey basis

 

 